Power Connection
The machine must be installed in a building that has protection against electrical malfunctions by a circuit
breaker, or an equivalent device. Such devices are necessary to give the machine protection for over-
current and short circuits.
Input Voltage Level:
120V, 60 Hz
15 A or more for the U.S.A. version
Permissible Voltage Fluctuation:
± 10%
Do not set objects on the power cord.
NOTES:
• Securely connect the power cord to a power source.
• Make sure that the wall outlet is near the machine and easily accessible.
• Make sure the plug is firmly inserted in the outlet.
• Do not pinch the power cord.
• Avoid multi-wiring.
• The required wall outlet is a NEMA 5-15R (receptacle)
Installation Times
Unit
Installation Time
(minutes)
Unit
Installation Time
(minutes)
Mainframe
20 minutes with 2 persons
Table
5 minutes with 2 persons
Roll Feeder
20 minutes with 2 persons
Printer
Controller
70 minutes
Hard Disk
35 minutes
Paper
Cassette
15 minutes
Interface
Board
10 minutes
Stamp
Board
10 minutes